As is - before move
in
Demo day on April
1st!
Ready to start
primer coat - April 3rd
First coat of primer
going on - April 4th
Removing glass film
First primer coat complete
2nd & 3rd coat of
primer on / ready for color - April
5-7
New color going on! - April
8 - 10th
Back room
construction - April 11th
Construction complete - April 18th
New cases and shelving
- May 1st - 4th
New wall slot-board
installed - May
13th
New back room
entrance door -
May 13th
New back room
pallet racking -
May 19th
Close to opening - May 25th
Open on June 1st
December 2017 - New Building Face lift
We Got a Facelift!