As is - before move
in



Demo day on April
1st!




Ready to start
primer coat - April 3rd

First coat of primer
going on - April 4th

Removing glass film

First primer coat complete

2nd & 3rd coat of
primer on / ready for color - April
5-7

New color going on! - April
8 - 10th


Back room
construction - April 11th



Construction complete - April 18th


New cases and shelving
- May 1st - 4th






New wall slot-board
installed - May
13th




New back room
entrance door -
May 13th

New back room
pallet racking -
May 19th


Close to opening - May 25th
Open on June 1st
December 2017 - New Building Face lift
We Got a Facelift!