As is - before move in

       



         


Demo day on April 1st!

         

        

 




Ready to start primer coat - April 3rd




First coat of primer going on - April 4th



Removing glass film


First primer coat complete



2nd & 3rd coat of primer on / ready for color - April 5-7

    


New color going on! - April 8 - 10th

    

         


Back room construction - April 11th

    

    

    


Construction complete - April 18th

       




New cases and shelving  -  May 1st - 4th



      



       






New wall slot-board installed  -  May 13th










New back room entrance door  -  May 13th




New back room pallet racking  -  May 19th

    

 

Close to opening  -  May 25th

  

 

Open on June 1st